Posted on: February 6, 2020

[ARCHIVED] 2020 project update from Street & Stormwater and Wastewater Departments

Zionsville

Below are updates from the Town of Zionsville Street & Stormwater Department and Wastewater Department regarding 2020 projects. All projects are subject to change with updates posted on a daily basis.


For updated information and a map, please visit: www.zionsville-in.gov/493/Key-Road-Projects


Boone County Highway Department Project:


Sycamore Street Bridge Rehabilitation

The reconstruction project for the Sycamore St. bridge is scheduled to begin Feb. 10, 2020. The official detour will utilize US 421/Michigan Rd., 106th St. and Main St.


Road closures anticipated:

Sycamore St. will be closed between Zionsville Rd. and US 421.

  • The trail system under the bridge connecting Lions Park to Creekside Park will be closed.
  • The pedestrian bridge and trail system along Sycamore St. are anticipated to remain open to the public with only periodic closures for safety.

Estimated completion: Aug. 28, 2020


Background: This project involves the reconstruction of the road bridge deck and bridge railing systems and provides new decorative lighting on the rehabilitated bridge.


Town of Zionsville Street Department and Wastewater Department Projects:


Zionsville Road

The road opened to all traffic on Dec. 23, 2019. While roadwork has been suspended for the rest of the winter season, Duke Energy will continue to install the decorative street lights. Final construction activities will take place in spring 2020.


Road closures anticipated: No further full closures expected


Estimated completion: May 2020


Background: This project involves the widening of Zionsville Rd., which will go from two to three lanes when a center turn lane is added between Technology Center Dr. and 106th St. The project also includes adding a bike path on the west side of the road.


North-South Connector

Bids have been awarded and contract documents are being finalized. Preliminary construction activities are expected to begin in February 2020 and full construction is expected in spring 2020. The project is anticipated to take a full construction season.


Road closures anticipated:

Intersection of Whitestown Rd. and CR 875 E. from June 1 - Aug. 1, 2020

CR 875 E. between CR 550 S. and CR 575 S., dates TBD

CR 850 E. south of Oak St., dates TBD

 

Estimated completion: September 2020


Background: Design has begun on a new roadway segment that will connect the intersection of CR 850 E./Cooper Rd. with CR 875 E. to the north. The design includes a roundabout at the intersection of 850 E./Cooper Rd. and Oak St. as well as a roundabout at the intersection of CR 875 E. and Whitestown Rd. The project is also expected to include a 10-foot multi-use path.

 

CR 400 S. Reconstruction and Widening

This project is postponed to late summer 2020 to allow Boone County REMC to complete the relocation of utility poles. Due to their restrictions in scheduling power outages necessary to complete this work, they cannot begin until May 1, and require eight to 10 weeks to complete tasks. Road reconstruction cannot begin until all utility poles have been moved.


Road closures anticipated: Full road closure of CR 400 S. for approximately .5 miles west of CR 875 E. is expected, dates TBD.


Estimated completion: Fall 2020

 

Background: This project includes the widening, repair and resurfacing of CR 400 S. to the west of CR 875 E. for approximately .5 miles.


CR 500 S. Reconstruction and Widening

Design is ongoing. It is anticipated that the utilities will be relocated over the winter with road construction beginning in summer 2020.


Road closures anticipated: Full road closures are anticipated.

 

Estimated completion: Fall 2020

 

Background: This project improves and widens CR 500 S. from CR 875 E. approximately 0.4 miles to the west. This project will reconstruct a portion of the road and widen the existing width to 24 feet. This project is funded partially from private developer funds.


Ford Road and Bloor Lane Roundabout

Work is nearly complete on new landscape and hardscape elements within the center of the roundabout.


Background: This roundabout includes low masonry walls and upgraded plant materials. The tree at the center that was planted by a local Eagle Scout candidate will be preserved.


Irongate Drainage and Improvement Project

A pre-construction took place in February. Because this project includes a new storm sewer pipe crossing under Oak St., traffic control personnel will be utilized during this portion of the project in order to keep Oak St. open traffic. Local access for residents and businesses within the project area will be maintained, but short-term driveway closures will be necessary.


Road closures anticipated: No full-road closures are currently expected. The south lane of eastbound Oak St. will be closed during the construction between Irongate Dr. and the Walgreen’s entrance.


Estimated completion: TBD

 

Background: This project is intended to mitigate localized street flooding in the Irongate subdivision. The project involves the installation of a new storm sewer pipe along the south side of Oak St. from Irongate Dr. to just west of Ford Rd.


Mulberry St. Pathway

Design work is nearly complete for this multi-use pathway. Construction is expected to begin in spring 2020.

Road closures anticipated: None anticipated

Estimated completion: December 2020


Background: This pathway will be on the north side of Mulberry St. from Governors Ln. to the roundabout at the intersection of Ford Rd. and Mulberry St.

 

Municipal Services Building Pathway

Design work is nearly complete. It is expected that this project will be awarded for construction prior to the end of this year and construction to begin in spring 2020.


Road closures anticipated: None anticipated


Estimated completion: December 2020


Background: A multi-use pathway will be constructed along the west side of the Municipal Services Building. This project will provide a route from the sidewalk system along Parkway Dr. south to Starkey Trail.


Phase I Gravity Sewer on CR 875 E. 

This project is currently underway. The sewer extension connects the intersection of CR 500 S. with the Zionsville School’s sport complex just to the north.


Road closures anticipated: Closure at CR 500 S (Whitestown Road) immediately west of CR 875 E. on Feb. 10 – 12, weather dependent.


Estimated completion: Spring 2020


Phase 2 Gravity Sewer on CR 875 E.

Part of this project is tied to the North-South Connector project. This project begins at CR 550 S. and travels south picking up several existing homes via gravity. 


Estimated completion: TBD


Oak Street Sewer

The sewer will be located on the north side of Oak St. and will extend west of Cooper Rd. traveling east to just west of Irish Hill. This project went out for bid in January 2020. A preliminary schedule will be announced soon.

 

Estimated completion: End of 2020


North Regional Sewer

This project takes sewer to the northeastern sewer service area of town through the Holliday property. This project is expected to go out for bid in February 2020.


Estimated completion: July 2020

Click Here for Full Press Release