For Phase I, construction is expected to begin on or around October 1, 2022 and be completed with all sewers operational and available for connection by the end of January 2023. No full road closures are expected. There are six general areas included in this project. Work will jump between these areas based on material availability. The general phasing sequence is expected to be:
- Sycamore Ct./White Oak Ct.
- Eaglewood Dr.
- Lakeview Dr./Karen Dr.
- Russel Lake Dr. East & West
- Mulberry St./Colony Ct.
- CR 850 E
Note: this does not mean that these areas will be completed and operational in that order. However, any area that is able to be completed and passes testing will be put into service as soon as possible.