A TOP NEWS ITEM

Posted on: July 21, 2017

Zionsville Road reconstruction project

The Town of Zionsville is developing a project to improve and widen Zionsville Road between 106th and Technology Center Drive. Construction is currently anticipated to begin in 2018, and all efforts are being made to meet that schedule. Among other reasons, the purpose and need for the project is to improve the overall safety of the arterial entrance into the Town of Zionsville.


Anticipated project schedule:

  • Right-of-Way Engineering/Land Acquisition: now - Dec. 2017
  • Design (Final Plans): now - Dec. 2017
  • Contract Awarded: Jan. 2018 - Feb. 2018
  • Utility Relocations: Feb. 2018 - May 2018
  • Construction Phase: Feb. 2018 - Nov. 2018


View exhibits of the proposed design. Zionsville Road TypicalZionsville Road Typical_vert



Click to View Zionsville Road Project Map