Sewer Extension Project

Areas Planned for Sewer Extensions


Phase I:

  • Eaglewood Drive
  • White Oak Ct
  • Sycamore Ct
  • CR 850 E
  • Rusell Lake Dr East and West
  • Lakeview Dr
  • Karen Dr
  • Colony Ct

Phase II:

  • Sycamore Bend Subdivision
  • Deer Ridge Subdivision
  • Boone Ridge Dr
  • Irish Hill Ln
  • Spring Hills Dr
Sewer Map

Timeline

All dates are subject to change. This chart will be updated regularly as new information becomes available.

Phase I 2021 2022 2023
Design and Permitting Oct. 2021 - Feb. 2022
Oct. 2021 - Feb. 2022  
Construction Funding Approval Dec. 2021    
Bidding and Award   March 2022 - May 2022
 
Construction   Oct. 2022 - Jan. 2023

For Phase I, construction is expected to begin on or around October 1, 2022 and be completed with all sewers operational and available for connection by the end of January 2023. No full road closures are expected. There are six general areas included in this project. Work will jump between these areas based on material availability. The general phasing sequence is expected to be: 

  1. Sycamore Ct./White Oak Ct.
  2. Eaglewood Dr.
  3. Lakeview Dr./Karen Dr.
  4. Russel Lake Dr. East & West
  5. Mulberry St./Colony Ct.
  6. CR 850 E

Note: this does not mean that these areas will be completed and operational in that order. However, any area that is able to be completed and passes testing will be put into service as soon as possible. 

Phase II 2021 2022 2023
Design Funding Approval Dec. 2021    
   
Design and Permitting   Aug. 2022 - Feb. 2023
Aug. 2022 - Feb. 2023
Construction Funding Approval Dec. 2021    
Bidding and Award     March 2023 - May 2023
Construction     June 2023 - Nov. 2023